Hey, Julia & JM
Welcome aboard!
Last update on: October 12, 2024
See what's the latest output from our team.
Accomplishment:
Site Visit carpentry team for actual measurements
Application for work permit and submission of pre-construction requirements.
Work in Progress:
Carcass of cabinetry works
What
Scheduling of removal of existing cabinetry
When
October 14 - 18, 2024
See what part of the project we are currently at.
Day 1
Initial Meeting & Consultation
Ocular Inspection
Day 2 - 21
Initial Design Perspectives
Bill of Materials
Production of Construction Drawings
Day 22 - 50
Work Permit and Gate Pass Acquisition
Construction Works
Furniture, Fixtures, & Accessories Placement
Day 50 - 52
Post Construction Cleaning
Final Inspection & Turnover
Who, what, and where?
Project Owner
Jose Mari Elises & Julia Meroy-Elises
Project
Kichen with Washer Dryer Combo
Renovation
Project Location
The Fort Victoria, 5th Ave, corner 23rd St
Taguig City